From Monday 14 April to Monday 2 June 2025, the Pustertal/val Pusteria railway will be closed on the section between Bruneck/Brunico and Innichen/San Candido.
The Italian infrastructure manager RFI will use this period to carry out modernisation, technical and safety work on the existing line. The European Train Control System (ETCS) will also be installed. Finally, the overhead lines will be replaced.
A replacement bus service will be provided throughout the works and closures.
Details of line closures
Closures | |
- Bruneck/Brunico-Innichen/San Candido line | 14 April 2025 - 2 June 2025 |
- Innichen/San Candido - state border - Sillian line | 14 April 2025 - 27 April 2025 |
The Franzensfeste/Fortezza-Bruneck/Brunico railway line will also be closed, probably until Saturday 13 December 2025.
Replacement bus service (Bruneck/Brunico-Innichen/San Candido)
B500 replacement buses run every half hour between Bruneck/Brunico station and Innichen/San Candido station. The replacement buses do not serve the railway stations (except Bruneck/Brunico, Olang/Valdaora and Innichen/San Candido), but the main bus stops in the various towns.
The hospital in Bruneck/Brunico is not connected to the replacement service, but is easily reached from Bruneck/Brunico railway station by several bus services.
Replacement bus B500 timetable Bruneck/Brunico - Innichen/San Candido
The SV223 replacement bus service runs hourly between Innichen/San Candido and Sillian stations.
Replacement bus SV223 timetable Innichen/San Candido - Sillian
Bike transport: Not allowed on replacement buses.
Information for people with reduced mobility is available HERE.
For more information, visit the Closures 2025 page or the Projects page.